More power is on the line for Glasgow.
A new transmission line that will supply additional electricity to the city is on schedule for a Nov. 30, 2009, completion date according to Nancy K. Mitchell, Tennessee Valley Authority manager for Valley Relations in the Kentucky District.
TVA will build approximately five miles of transmission line that will provide power to a new substation to be constructed by the Glasgow Electric Plant Board in 2009.
“Glasgow, right now, gets all of its power from TVA at the Haywood substation,” explained EPB superintendent Billy Ray. “The new line is for us to build a new substation that we’re tentatively calling the East Glasgow Primary.”
The east Glasgow substation will be built on property given to EPB by the city on Ky. 63 where the city dump used to be, close to the Cumberland Parkway overpass.
Ray said the new transmission line will come from TVA’s existing east-west line that travels from Bowling Green to Summer Shade and out off Bristletown Road where they will tap into it. The line follows a general north-northwest path from there toward the new substation site. It will run roughly parallel and to the east of Roseville Road much of the way.
About half of the new line will be built on a right of way that the plant board already owned for a lower voltage transmission line.
“We gave (TVA) that right of way as an enticement for them to build the line,” Ray said. “So we’ll be taking down our old transmission line and they’ll be building this new one on the same piece of property.”
The old 69kV transmission line that EPB owned leads from Haywood to the Gorin Park substation. EPB is relinquishing it to TVA and they will use that right of way and tear down the old line to build a new 161kV line to serve the new substation. Ray said EPB plans to retire the Gorin Park substation after the new one is online.
The new transmission line and substation will not only provide additional power to the city, according to Ray, but also serve as a backup in EPB’s redundancy plan in case of power outages at the Haywood site due to severe weather or other disasters.
TVA plans to start putting up lines in the spring after all easement issues are finalized with property owners, according to Mitchell.
Ray anticipates construction on the new substation will be completed in November 2009 as well.
“When they get that transmission line completed and energized, we want it to tie right into our new substation,” he said.
Local News
Where does the power line go?
- Local News
-
-
Ambulance board OKs outsource billing
After a thorough discussion during Wednesday’s board meeting, the Barren-Metcalfe Emergency Medical Services decided to outsource its billing to AMB-MARS (Medical Accounts Receivable Systems doing business as AMBulance Medical Billing), contingent on AMB-MARS adding a guarantee clause on its work.
-
Teen named local youth of the year
Rayne Triplett has been practicing the speech she will give at the end of the month when she travels to Frankfort to compete for the Boys and Girls Club’s 2012 State Youth of the Year title.
-
Howard lauded for G/T work
Glasgow Superintendent Sean Howard was presented the Kentucky Association for Gifted Education’s Michael Caudill Educator Award on Monday at the annual KAGE conference in Lexington.
-
Teens to be tried as adults
Barren Circuit Court released the names of two juveniles charged in an armed robbery in October, after the court decided to try the teens as youthful offenders in adult circuit court.
-
Payne pleads guilty to lesser charge
A Glasgow man who had been facing a felony charge of custodial interference pleaded guilty Tuesday in Barren Circuit Court to a lesser charge.
-
Rowland will take Comer's seat for now
A Monroe County businessman will fill the unexpired term of former state representative Jamie Comer, according to the results of Tuesday’s special election.
-
County struggles to provide EPA report
Barren County Road Department Head Johnny Kinslow called his bi-monthly report to the fiscal court his “gloom and doom” report Tuesday night. After five years of letters and discussions, the Environmental Protection Agency has informed Kinslow that he must produce a closure report for underground fuel tanks that were removed 13 years ago, or face unnamed consequences.
- MORNING UPDATE: Two juveniles charged as adults in robbery
- MORNING UPDATE: Tebben blogs from New York
-
Chamber names Travis ‘Outstanding Citizen’
Winning the Outstanding Citizen of the Year Award Monday night came as a complete surprise to Dr. Bill Travis.
- More Local News Headlines
-
Ambulance board OKs outsource billing